News & Project Updates

  • Weekly Update 2nd March

    Weekly Update 2nd March

    Construction activity for the week included; 18 of 53 WTG now complete. 26 WTG base and mid tower sections erected. 49% of the turbine components (blades, hubs, towers) delivered to site. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing o…

    Read more »
  • Weekly Update 23rd February

    Weekly Update 23rd February

    Construction activity for the week included; 17 of 53 WTG now complete. 25 WTG base and mid tower sections erected. 47% of the turbine components (blades, hubs, towers) delivered to site. 49 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing o…

    Read more »
  • Weekly Update 16th February

    Weekly Update 16th February

    Construction activity for the week included; 15 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 48 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing o…

    Read more »
  • Weekly Update 9th February

    Weekly Update 9th February

    Construction activity for the week included; 13 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 45 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing o…

    Read more »
  • Weekly Update 2nd February

    Weekly Update 2nd February

    Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 12 of 53 WTG now complete. 23 WTG base and mid tower sections erected. 41% of the turbine components (blades, hubs, towers) delivered to site. 44 of 53 foundations poured. Excavation…

    Read more »
  • Weekly Update 19th January

    Weekly Update 19th January

    Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine ac…

    Read more »
  • Weekly Update 12th January

    Weekly Update 12th January

    Construction activity for the week included; Partial site activities commenced on 3rd January, with full operation commencing 8th January. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations contin…

    Read more »
  • Weekly Update 20th December

    Weekly Update 20th December

    Construction activity for the week included; Site shutdown from 22-12-2017 to 3-01-2018, with full operation resuming 8-01-2018. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Back…

    Read more »
  • Weekly Update 13th December

    Weekly Update 13th December

    Construction activity for the week included; 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 41 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for…

    Read more »
  • Weekly Update 6th December

    Weekly Update 6th December

    Construction activity for the week included; 5 of 53 WTG now complete (WTG 3,4,5,8,9) with WTG 6, 7, 14 and 15 expected in next two weeks. 40 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of e…

    Read more »