24 hour community call line: 1800 280 013
Mt Emerald Wind Farm

Weekly Update 19th January

Weekly Update 19th January

Construction activity for the week included;

  • 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected.
  • 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.
  • Continuation of earthworks for turbine access roads; approximately 78% of clearance works complete
  • Construction of substation and switchyard continuing. Main transformers due for placement in coming weeks.
  • Placement of underground cabling continuing
  • Works continue on upgrades to Site Entry Road (intersection to site compound) including vegetation of batters
  • UXO, Cultural Heritage and Environmental aspects continue prior to vegetation clearance in new areas.
  • Component deliveries included blades, hubs and towers.
  • 76 pieces of heavy equipment on-site.
  • Personnel on-site averaged 212.
MEWF Weekly Update 19th January
📄
Download the document: 20180119-MEWF-Weekly-Update.pdf
← Weekly Update 12th JanuaryWeekly Update 2nd February →