24 hour community call line: 1800 280 013
Mt Emerald Wind Farm

Weekly Update 26th April

Weekly Update 26th April

Construction activity for the week included;
• Main access road - clearing and grubbing, profiling,
sub-base works for Chainage 400 - 1700
• Commencement of earthworks for upper laydown area
• Excavation of the first wind turbine foundation (WTG#3)
• Bulk earthworks commenced for Powerlink bench for connection to the electricity grid
• Clearing of spur roads to wind turbine locations from main access road continues
• Clearing, weeding controls and other environmental requirements in accordance with management plans are being implemented and maintained as necessary.
• Field survey work continues for UXO, Cultural Heritage and Environmental aspects prior to vegetation clearance in new areas
MEWF Weekly Update 26th April

📄
Download the document: 20170426-MEWF-Weekly-Update.pdf
← Weekly Update 19th AprilWeekly Update 3rd May →