Construction activity for the week included;

  • Earthworks at Powerlink substation bench complete. Powerlink taking over and established site.
  • Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling.
  • 9 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.
  • Continuation of earthworks for turbine access roads; approximately 52% of clearance works complete.

  • Work continuing on intersection upgrade work at Kippen Dr / Springmount Rd.
  • Works commenced on upgrades to Site Entry Road (intersection to site compound)
  • Field survey work continues for UXO, Cultural Heritage and Environmental aspects prior to vegetation clearance in new areas.
  • Quoll detection dogs now being used to clear areas before construction.Tracking of collared individuals continues.
  • 54 pieces of heavy equipment on-site. Personnel averaged 103. 250 people inducted for site.