24 hour community call line: 1800 280 013
Mt Emerald Wind Farm

Weekly Update 26th July

Weekly Update 26th July

Construction activity for the week included;

• Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. Crushing of cap delayed due to Quoll in rack stockpile.

• Site Access Road. Road up the hill is nearing a point where it can now be used for access.
• Continuation of earthworks for turbine access roads; approximately 41% of clearance works complete.

  • Delivery of electrical cable, culverts, reinforcement and foundation bolt assemblies arriving at site
  • Work continuing on intersection upgrade work at Kippen Dr / Springmount Rd.
  • Field survey work continues for UXO, Cultural Heritage and Environmental aspects prior to vegetation clearance in new area
  • Quoll detection dogs now being used to clear areas before construction
  • 39 pieces of heavy equipment on-site. Concrete batching plant delivered to site. Personnel totalled 79
PDF Embedder requires a url attribute
← Weekly Update 19th JulyMEWF - Newsletter #14 - August 2017 →