24 hour community call line: 1800 280 013
Mt Emerald Wind Farm

Weekly Update 16th August

Weekly Update 16th August

Construction activity for the week included;

  • Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer.
  • Site Access Road. Road up the hill is now open to be used for access.
  • First foundation (WTG #4) poured 11th August. Placing of reinforcing continuing at WTG 5, 7 and 8.
  • Continuation of earthworks for turbine access roads; approximately 42.5% of clearance works complete.
  • Work continuing on intersection upgrade work at Kippen Dr / Springmount Rd.
  • Field survey work continues for UXO, Cultural Heritage and Environmental aspects prior to vegetation clearance in new are
  • Quoll detection dogs now being used to clear areas before construction.
  • 42 pieces of heavy equipment on-site. Personnel totalled 100.
PDF Embedder requires a url attribute
← Mount Emerald Wind Farm reaches major construction milestone.Weekly Update 23rd August →